Canby's primary north-south thoroughfare under construction for sewer main replacement through mid-January

GOOGLE SATELLITE IMAGE - Those looking to travel along South Ivy Street will see delays through mid-January as the sewer main is replaced along the thoroughfare.

If you frequently drive South Ivy Street in Canby, plan some extra time for the drive over the next couple of months.

Canby's Public Works department is using a contractor to replace the sewer main on South Ivy Street. Construction began Nov. 12 and continues through Jan. 11.

During that timeframe, the road will be closed at different times throughout the day, and only local traffic will be allowed.

Expect delays, and use detour routes along 99E/Southeast 2nd Street, South Pine, Southeast 13th Avenue and South Elm Street.

COURTESY PHOTO: CANBY PUBLIC WORKS - The Canby Public Works department recommends the pictured detour routes for drivers.

According to the construction schedule, sewer installation will take place through Dec. 23. Then curb installation, concrete surfacing, asphalt paving and cleanup will take place from Dec. 28 through Jan. 11.

The schedule is subject to change, however, due to weather or other unforeseen circumstances.

Those with questions or concerns may contact Public Works at 503-266-0798.


Kristen Wohlers
Reporter
503-263-7512
email: This email address is being protected from spambots. You need JavaScript enabled to view it.


You count on us to stay informed and we depend on you to fund our efforts. Quality local journalism takes time and money. Please support us to protect the future of community journalism.

Go to top
JSN Time 2 is designed by JoomlaShine.com | powered by JSN Sun Framework